Local Road Management Manual 550 V. Daily Production Rate - 12 cu. m. of patching placed VI. Method of Measurement The quantity of manual patches of shoulders to be paid shall be the total cubic meters of materials which have been consumed and accepted by the Engineer. VII. Basis of Payment The quantity of completed patching of and compacted shoulder as provided above shall be paid for at the contract unit price per cubic meter. Payment shall constitute full compensation for providing, transporting, placing and compacting of the road shoulders, and for all labor, equipment, tools to complete this item, including the required traffic control. VIII. Payment will be made under: